Many orders with Chinese suppliers are placed on the supplier's proforma invoice, listing the product, quantity and price, and nothing about quality, inspection or what happens if the goods are wrong. Then, on inspection day, the factory says the buyer never asked for an inspection, or disputes what "acceptable" means. The protection has to be agreed before the deposit is paid. This guide lists the inspection clauses worth putting in a purchase order, with example wording.

What this article covers
  • Why a proforma invoice is not enough
  • Seven inspection clauses for a China purchase order
  • Example wording to adapt

Why the Proforma Invoice Is Not Enough

A supplier's proforma invoice is written to describe the sale from the supplier's side. It rarely says how quality is judged, who can inspect, or what happens after a failed result. Issue your own purchase order, or a short quality agreement attached to the order, and have the supplier sign or stamp it before the deposit is paid.

Important: the wording below is an example to adapt, not legal advice. Contracts with Chinese suppliers raise questions of governing law, language and enforcement. Have a lawyer familiar with China trade review your terms.

Seven Clauses Worth Including

1. Inspection access

The buyer or its appointed inspector may inspect the goods at any stage of production at the production site, including materials, work in progress and finished goods, with reasonable notice.

2. Acceptance standard

The goods will be inspected against the approved sample, the specification and the inspection checklist attached to this order, using ISO 2859-1 sampling at General Inspection Level II with AQL 0 for critical, 2.5 for major and 4.0 for minor defects, unless otherwise stated. The AQL guide and defect classification guide explain these terms.

3. Production site

The goods will be produced at [factory name and address]. Production at any other site, or subcontracting of any main process, requires the buyer's prior written approval. See our guide to unauthorised subcontracting.

4. Materials and changes

Materials, components and processes will be as specified. Any change requires the buyer's prior written approval, even where the supplier considers the change equivalent. Material certificates will be provided on request.

5. Re-inspection

If the goods fail inspection, the supplier will correct them at its own cost, and the cost of re-inspection will be borne by the supplier, either paid directly or deducted from the balance.

6. Authorisation to ship

The goods will not be shipped without the buyer's written authorisation to ship, which will be given after a passed inspection.

7. Payment

The balance will be paid within [number] working days of a passed inspection report and authorisation to ship. Our article on why the balance should wait for inspection explains why.

SSTI inspector checking metal discs on a factory production floor
An SSTI inspector during a factory visit. The photo is illustrative.

Make the Clauses Work in Practice

SSTI works from your checklist and PO terms on the factory floor. See our inspection services, or contact us to discuss an order.

Setting up a new supplier?

SSTI inspects against your PO terms and checklist on the factory floor, anywhere in mainland China.

Talk to SSTI

Back to Insights